Galan Lithium: Can HMW Project's Steady Strides Pave the Way for H1, 2025 Production?
Galan Lithium Limited
1 1

Galan Lithium: Can HMW Project's Steady Strides Pave the Way for H1, 2025 Production?

Post image

Galan Lithium Limited's Ambitious HMW Project: Aiming for H1, 2025 Lithium Production

Galan Lithium Limited (ASX: GLN) has marked significant strides in the construction activities at the Hombre Muerto West (HMW) Phase 1 lithium brine project, aimed at establishing lithium chloride production by the first half of 2025. The project is progressing at a steady pace, showcasing substantial advancements across various key construction segments.

Advancing Construction Milestones:

Pond 1 construction, a pivotal component of the project, is notably making strides with an impressive 65% completion rate. Liners crucial for the construction process have arrived on-site, and their installation is scheduled to commence later in December 2023. Expectations are set for the fill of Pond 1 in Q1, 2024, with the evaporation process scheduled to kick off during the upcoming summer season.

Preparation for Future Phases:

Simultaneously, groundwork for Ponds 2 and 3 is underway, including the ongoing process of topsoil removal, signifying the proactive stance of Galan in preparing for future project phases. The development of new camp and essential infrastructure is also progressing smoothly, with all final modules substantially in place.

Story Continues.. after this ad because we need some dollarydoos





Technical Due Diligence and Management Outlook:

Furthermore, Glencore's technical due diligence has commenced, indicating an important stage of assessment and validation for the project.

Juan Pablo (JP) Vargas de la Vega, Galan's Managing Director, expressed satisfaction and optimism during his visit to the site this week. He commended the remarkable progress made on-site, highlighting the dedication and proficiency exhibited by the project team. Vargas de la Vega emphasized the expertise and cohesion within the team, essential for constructing the ponds and infrastructure needed to accomplish the project's objectives.

Driving Towards First Production:

"We are sharply focused on our objective to commence brine evaporation this summer," said Vargas de la Vega. He conveyed Galan's unwavering enthusiasm and confidence in the development of Phase 1 HMW, reaffirming the company's commitment to achieving the targeted first production milestone in the first half of 2025.

Galan Lithium's strategic approach, paired with the determined execution of construction plans and the assembling of a capable and skilled workforce, paints an optimistic picture for the company's successful foray into lithium production, poised to make waves in the burgeoning lithium market.

Promote your business on our growing investor platform: Advertise With Us
Trending